| No | Step | Duration | |
| 1 | ![]() |
Excavations for The Foundation | 1-3 weeks |
| 2 | ![]() |
Laying of The Foundations | 15-30 days |
| 3 | ![]() |
Concrete for Each Floor | 7-10 days |
| 4 | ![]() |
Walls & Isolation | 15-30 days |
| 5 | ![]() |
Installation of Water Pipes | 2-3 weeks |
| 6 | ![]() |
Plaster & Installation of Heating | 20-30 days |
| 7 | ![]() |
Doors & Windows | 1-2 weeks |
| 8 | ![]() |
Floors | 3-4 weeks |
| 9 | ![]() |
Painting | 20-30 days |
| 10 | ![]() |
Finishing | 2-3 weeks |